Monday, May 28, 2012

Day 124 , May 19

The day the drywall arrived, the guys tried to bring it up the hill to the driveway.  Only problem is that the truck was so heavy and the stack was so high, it couldn't sit on the hill without slipping.  The guys ended up bringing the large trailer of drywall to the base of the property and loading it onto a different (smaller truck), then drove it back up to the driveway and unloaded a second time.  There were multiple sizes, the largest being about 5x12 feet.  









2 comments:

  1. How long did it take for them to put up the drywall?
    Was it just one day?

    ReplyDelete
  2. 2 guys & 3 days, maybe? They did most of it themselves, and used a lift for the high-up portions. The cool part is the arched ceiling in the front hallway. Instead of a thick piece of drywall they used 3 very thin ones so it would bend.

    ReplyDelete